Kardem Tekstill Factory
they invest in hybrid green power from solar by implement roof type solar panel on the factory , with our soultion with following benifits
- fixed power to main
- Min. Load on genertaor to save fuel when main off
- max. pv power from inverter
- power management , when amin off to prevent voltage rise
Royalstar Energy Systems has successfully implemented and commissioned the Hybrid Control Panel project for the solar power plant with an installed capacity of 1.2 MW in the KARDEM Textile Factory in Edirne Keşan.
Grid, Solar System and Generator work together synchronously.
The surplus of energy produced from solar energy during the day is exported to the grid. In case of a possible power outage, the generator is automatically activated and solar energy continues to be produced. The generator is operated with minimum power and solar energy is utilized at the maximum level. In this way, both the generator saves fuel (the cost is downward) and the solar energy production meets the consumption without interruption.
The system works fully automatically.
solar hybrid synchronization panel
the panel with deif controlelr and indestrial PC make full star/staop of system amd make full power management of ABB Solar inervter to insure the function above
ABB inverter 100 kw
ABB inverter with build in combined box for DC strip and AC 400 v connected to totalaizing panel fo 12 inverter , with out Mian breaker
the system work with ABB weather station