Petronas Malaysia/Nasria 2009

petronas  projects  Garraff – iraq 

1- 2009  camp diesel power station : 2000 kw 

ROYALSTAR  start Project with Petronas  in  15/01/ 2009 ,EPC supply and instaltion the camp power station as non-stop diesel power station , work with full power management automaticly  start/sop  generators , also change between each others  depending on load and time to save fuel and insure equal ageing of generators.

The Project was approved from Petronas and award us 2nd project  28 MW , the refinery  power plant  with 14 DG  x 2000 kw , after  Success  the first project  of camping .

perkins generators 500 kw

perkins generators 500 kw

Hover Box Element

Royalstar supply 4 generator with capacity 500 kw work in parallel, to save fuel , when load low only one generator work

deif synchronization-panel

Deif Agc 3 controller

DEIF AGC 3

The project was designed by use DEIF AGC 3   upgrade in 2014 to work in parallel with Main by use Deif controller type AGC-3 for forward and back work synchronize with main, can export to main with fixed power Very smooth efficient system.

DEIF  AGC-3

The project was designed by use DEIF AGC 3   upgrade in 2014 to work in parallel with Main by use Deif controller type AGC-3 for forward and back work synchronize with main, can export to main with fixed power Very smooth efficient system.

deif  HQ Gas generator

application of  deif gas controlller for small  Man Gas generator in deif Denmark office work on natural gas to supply  factory , also export to grid network  the rest of power   as green  source of  power .